Date
17 August 2023
Project
Wellingborough Deconstruction
Wellingborough Deconstruction Project Complete
The two final deconstruction milestones have been completed on the Wellingborough Project over the last week.
The Vincere Training and Business Solutions team led by Will Patterson – Grad IOSH, AIEMA safely and successfully top and tailed the 26T Boiler and placed onto the special vehicle that is enroute to the Client.
A big thankyou to FJ Crane Hire Ltd and Philip Framp for executing the contract lift safely and efficiently.
A big thankyou to Allelys Nathan Clarke for the transportation and transport / loading studies.
A big thank you to Ben Fellowes and Trevor Cail for the P.D and Temp Works design support for these two milestones and also for their support through the Project.
#healthandsafetyatwork #teamworkmakesthedreamwork #heavymachinery #cranesafety