The two final deconstruction milestones have been completed on the Wellingborough Project over the last week.

The Vincere Training and Business Solutions team led by Will Patterson – Grad IOSH, AIEMA safely and successfully top and tailed the 26T Boiler and placed onto the special vehicle that is enroute to the Client.

A big thankyou to FJ Crane Hire Ltd and Philip Framp for executing the contract lift safely and efficiently.

A big thankyou to Allelys Nathan Clarke for the transportation and transport / loading studies.

A big thank you to Ben Fellowes and Trevor Cail for the P.D and Temp Works design support for these two milestones and also for their support through the Project.