A really important couple of weeks on the Wellingborough Project and the last 2 major milestones behind the team and safely delivered.

The 26te Boiler is as lifted out through the roof and then topped and tailed, prior to landing at grade. The team then lifted the 12te boiler bed out ready for transportation.

Very safe lifting operations with the Projects Crane partner TERRANOVA CRANE SALES LTD

Very effective management by the Vincere Training and Business Solutions meant that another complex lift was very safely executed. Well done to the Site team of Will Patterson – Grad IOSH, AIEMA Dave Lavery CMIOSH, IQA, IMaPs, DipRSA and John Costello.

Our Client Rotamac EPC Energy Solutions Ltd we’re very happy with the safe completion of the boiler removal.