Wellingborough Biomass Plant – Deconstruction Project Update

News

Date

Project
Wellingborough Deconstruction

Wellingborough Biomass Plant – Deconstruction Project Update

Through Vincere Training and Business Solutions existing 3 year working partnership with Rotamac EPC Energy Solutions Ltd, we have been contracted to provide the Project team for the Clients deconstruction Project in Wellingborough. Vincere Training and Business Solutions is undertaking the Project, (de)Construction, H&S and Management systems delivery, for the Project.

Other key services being provided are Lifting & Rigging, Ecology, Asbestos, Structural Engineering and Temporary Works design / coordination.

The Project execution phase started on the 2nd January and is due to last 14 weeks, with the pre-construction phase commenced in early October 2022. The Bio Mass equipment that is being deconstructed, matchmarked and packaged, is then being safely transported to a Construction site in Bulgaria on behalf of the end Client.

Vincere have a team of 6 full time personnel dedicated to the project, and have introduced a strong supply chain and an experienced team of blue collar workers to our Rotamac EPC Energy Solutions Ltd Client. This is Vincere’s fourth such Project supporting Rotamac EPC Energy Solutions Ltd and looking forwards to a safe and successful completion of the Project and working with our great client on future Projects.

Jason Blood BEng (Hons) MAPM GradIOSH MCIOB with Vincere Training and Business Solutions Senior Construction Site Manager Will Patterson – Grad IOSH, AIEMA early in the New Year.