Wellingborough Biomass Plant – Deconstruction Project Update

News

Date

Project
Wellingborough Deconstruction

Wellingborough Biomass Plant – Deconstruction Project Update

The Project team have had another busy week so far in removing part of the superstructure in readiness for the 32T tail end to be lifted down to grade.

Careful cutting on the water tube boiler commences early next week, prior to the 26T boiler being lifted out through the roof.

Crane mat and pre-enabling works will be finished in readiness for the lift.

Great teamwork led byΒ Will Patterson – Grad IOSH, AIEMAΒ John CostelloΒ andΒ Christopher BaxterΒ πŸ‘πŸ»πŸ‘πŸ»