Wellingborough Biomass Plant – Deconstruction Project Update
Will Patterson – Grad IOSH, AIEMA and the Project team had a busy Saturday and Monday getting the roof modifications completed ready for the 12T Furnace and Superheater Dome being removed on Thursday.
The scaffolding and roofing team have worked safely to ensure safe access and safe opening of the roof to allow the cranes to remove the Dome this week and also the tail end of the boiler next week.
Thank you team for the continued safe deconstruction of the Biomass plant on behalf of the Client Rotamac EPC Energy Solutions Ltd