Wellingborough Biomass Plant – Deconstruction Project Update

News

Date

Project
Wellingborough Deconstruction

Wellingborough Biomass Plant – Deconstruction Project Update

The Vincere Training and Business Solutions and Rotamac EPC Energy Solutions Ltd Project team have been continuing the Wellingborough Deconstruction Project.

Complex deconstruction and lifting activities have continued pre and post the Easter celebration, and key Project milestones have been safely achieved.

The Air Filtration unit (baghouse), Pre-heater, boiler bed and Steam Drum have all been deconstructed and safely brought down to grade and transported to the continent.

A quick thankyou to out crane partners TERRANOVA CRANE SALES LTD and BALDWINS CRANE HIRE LIMITED for providing quality crane services in a tight environment.

Special thanks as always goes to the Vincere Training and Business Solutions team of Will Patterson – Grad IOSH, AIEMADave Lavery CMIOSH, IQA, IMaPs, DipRSAJohn Costello and Rotamac EPC Energy Solutions Ltd team of Christopher Baxter Matthew Baxter and Stephen Baxter for their Client support.

The Project just has the boiler and tail end to deconstruct over the next three weeks.

#business #energy #team #sales #quality #thankyou #training #project #environment #biomass #deconstruction #safetyculture #grateful #greatteamwork

Menu