Wellingborough Biomass Plant – Deconstruction Project Complete

The two final deconstruction milestones have been completed on the Wellingborough Project over the last week. The Vincere Training and Business Solutions team led by Will Patterson – Grad IOSH, AIEMA safely and successfully top and tailed the 26T Boiler…

Wellingborough BioMass Plant Deconstruction Project Update

News It has been a busy last couple of weeks for the Project Team at Wellingborough. The roof has been reinstalled following its removal to allow safe lifting of the Boiler and Tail End units. The roof has been reinstalled…

Wellingborough Biomass Plant – Deconstruction Project Update

The final big lift for the Wellingborough Deconstruction Project has been safely and successfully completed for the Client. The 50te Tail End of the Boiler was safely lifted down to grade using the Projects crane partner TERRANOVA CRANE SALES LTD…

Wellingborough Biomass Plant – Deconstruction Project Update

Today has seen another significant and complex deconstruction milestone completed by the Vincere Training and Business Solutions team on the Wellingborough Project. The 13te Furnace / Superheater Dome was safely lifted to grade in a tandom lift, using our contract…

Wellingborough Biomass Plant – Deconstruction Project Update

Will Patterson – Grad IOSH, AIEMA and the Project team had a busy Saturday and Monday getting the roof modifications completed ready for the 12T Furnace and Superheater Dome being removed on Thursday. The scaffolding and roofing team have worked…

Wellingborough Biomass Plant – Deconstruction Project Update

The Vincere Training and Business Solutions and Rotamac EPC Energy Solutions Ltd Project team have been continuing the Wellingborough Deconstruction Project. Complex deconstruction and lifting activities have continued pre and post the Easter celebration, and key Project milestones have been…

Wellingborough Biomass Plant – Deconstruction Project Update

Great progress on the Wellingborough Project continues with two key milestones achieved late last week. The Turbine & Generator were safely and successfully deconstructed, lifted, wrapped and placed on special vehicles for their trip to Bulgaria. The Rotamac EPC Energy…